Merchants Transfer

Project Description

Just over 2 years after fire destroyed the original structure, we wrapped construction on a new 274,212 square-foot warehouse for Merchants Transfer Company—on an accelerated 11-month timeline.

The facility, designed for leasing and long term logistics use, features pre-engineered metal buildings divided by 12" CMU fire separation walls to ensure safety and flexibility. One of the biggest challenges was preserving and utilizing as much of the existing slab as possible, a task our team tackled with precision and problem-solving from day one.

At Rogers & Willard, building smarter and faster is never at odds with building better. This project reflects our core values in action: relentless progress, whatever it takes, and delivering meaningful work that supports our clients’ future.

Client: Mac Taul - Merchants Transfer Company

Architect: Clark Geer Latham & Associates, Inc.

Date: 2025

Category: New Build

  • 274,212 Sqft

  • Warehouse Leasing Space for Merchants Transfer Company

  • Pre-Engineered Metal Buildings separated with 12” CMU Fire Separation Walls

  • Challenges included utilizing as much of the remaining slab as possible

  • The original building burned down on June 19, 2023. R&W began construction on Sept. 4, 2024, and completed the project on July 8, 2025

  • Very accelerated timeline – 11 months start to finish

Other Warehouse Projects

  • Lear Corporation Logo
  • Ford Logo
  • Regions Bank Logo
We trusted Rogers & Willard with a major project, and they exceeded our expectations. Their excellent communication and consistent follow‑through made the entire process smooth, handled with true professionalism and honesty.
— Mac Taul, Merchants Transfer